Canned Fruits Production Flow Chart

Second Part of the Procedure

Water transport of fruits to the calibrators of  half fruits
Calibration of half fruits in sizes
Forwarding of calibrated fruits to final inspection lines
Final control of defected fruits
Final control of pit fragments CCP3
Filling of tins with fruit
Weighing of tins
Filling of tins with syrup CCP2, 4, 5
Filling of tins with syrup under vacuum
Removal of air with exhauster CCP5
Removal of air
Control of exhauster temperature CCP5
Seaming of tins CCP5
Control of tin seaming CCP5
Pasteurization of product CCP6
Control of temperature and time of pasteurization CCP6
Cooling of product CCP6
Control of time and temperature of cooling CCP6
Final quality control of end product
Removal of water drops from the lid of the tin with air
Forwarding of end product in the warehouse
Setting of end product on pallets
Setting of pallets in the warehouse

Go back to the First Part

canned peaches

Home  |   FQCS  |  Canned Peaches  |  Canned Fruits  |  Vassilis  |  Contact

Production flow  |  FAQs  |  Order form  |   Recipes  |  Healthy tips   |  Site map

canned fruits
 
“ Copyright ©  FQCS - All rights reserved - 2011 ”